Scaling a Chromatography System from Pilot to Production

When moving a chromatography process from pilot to production, which functions need to move with it?

A pilot system may support different methods, experimental measurements and frequent changes in configuration. Production may require some of that flexibility, particularly in a multiproduct facility. The equipment specification needs to connect each selected function with its intended manufacturing use.

An additional buffer inlet illustrates the decision. Depending on the arrangement, it can involve a valve, a selection sequence, a cleaning route and checks to demonstrate correct operation. Its value depends on how production will use it.

Scaling a chromatography system therefore involves reviewing capacity and configuration together. Alongside the required operating range, consider how the equipment will be operated, cleaned, controlled and maintained throughout production.

 

Review Capacity and Configuration Together

Column dimensions, required flow range and pressure conditions provide essential input to the production system design. The assessment also needs to account for process liquids, temperature, gradient operation and pressure losses through the complete flow path.

Define the operating cases the equipment must support, including processing and cleaning. Where one system will serve several applications, identify the relevant ranges so that pumps, instrumentation and control can be assessed against them.

Alongside this capacity review, examine the functions used during pilot work. Some may be essential to the manufacturing process. Others may have supported development experiments or applications outside the current production plan.

Record the purpose of each proposed function. This gives the engineering team a basis for assessing the configuration and understanding where flexibility remains necessary.

 

Review Which Flow Paths Production will Use

Start with the required feed connections, buffer inlets, product outlets, waste routes and bypasses. For each route, describe when it is used, where the liquid comes from and where it needs to go.

A pilot installation may accommodate temporary connections and manual changes between runs. At production scale, consider how those activities will be performed with the intended liquid volumes, handling arrangements and operating procedures.

Buffer supply conditions also matter. An inlet connected to an atmospheric vessel presents different engineering conditions from one connected to a pressurised supply. Product collection requires a corresponding review of destinations, connections and line handling.

For a dedicated installation, the required routes may remain consistent throughout a campaign. A multiproduct system may need a broader range of selectable configurations. In both cases, follow the proposed routes through processing, cleaning and drainage before approving the arrangement.

 

Give Each Measurement a Defined Production Role

Pilot measurements can support process development, control and documentation. Review which of those roles each measurement will serve in production.

A pressure reading may inform the operator, regulate a pump, initiate a protective action or provide a recorded process value. The intended role influences the instrument range, accuracy, installation position and response to a lost or invalid signal.

Apply the same review to UV, conductivity, pH, temperature and flow measurements. Define how each reading will be used and whether it contributes to fraction collection, gradient control, alarms or batch records.

Consider the required operating range across all planned applications. An instrument suitable for one operating case may need further assessment when the same system must also support substantially different conditions.

Calibration and replacement deserve attention during the layout review. Establish whether instruments can be checked in place, how they can be isolated and what access is needed for removal.

 

Follow an Additional Buffer Inlet through the Complete Operation

Consider a buffer inlet used during pilot development. Before carrying it into the production specification, identify the manufacturing step or planned application it will support.

If the inlet is required, define its supply conditions, connection and materials. Establish whether selection will be manual or automated and how the selected route will be confirmed.

Then follow the inlet branch through cleaning. Determine how cleaning liquid reaches it, how the branch is drained and whether valves need to be operated in a particular sequence.

For an automated arrangement, describe the permitted switching conditions and the response if a commanded action is unsuccessful. Decide where valve position feedback is needed to support that operation.

Finally, identify how the function will be demonstrated. Depending on its role, verification may need to cover route selection, switching behaviour, feedback and associated alarms.

Following the inlet through these steps makes the implications of the design choice visible. The same approach can be applied to an additional fraction outlet, sample loop or bypass before the configuration is confirmed.

 

Connect the Configuration with Qualification

Flow paths, instruments and automated functions contribute to what needs to be verified before routine use. Qualification expectations therefore belong in the design review while the configuration is still being developed.

Process engineering, operations, automation and quality need a shared understanding of the intended functions and the evidence required to demonstrate acceptable performance.

EU GMP Annex 15 places user requirements and design qualification early in the equipment lifecycle. It also calls for a justified, documented risk assessment when determining the scope of qualification and validation.

Component count alone does not determine that scope. A single protective function may require substantial attention, while several straightforward connections may be assessed differently.

For the equipment review, connect each significant function with its intended use, the consequences of incorrect operation and the proposed means of verification.

 

Keep Flexibility where the Production Plan Needs It

Additional flexibility can be valuable when a system will support several products, different separation steps or a planned range of batch sizes.

Describe those applications as specifically as the available information allows. Expected flow ranges, pressure conditions, solvents, connections and control functions help turn a future application into an engineering input.

Consider the ongoing work associated with each option. An additional instrument may enter the calibration programme. An automated route may require further sequences and testing. Components added to the layout also need access for inspection and maintenance.

Where a future application is still being defined, discuss whether provision can be made for a later addition. The feasibility depends on the equipment architecture, site interfaces and the nature of the change.

The aim is to retain useful flexibility with a clear understanding of how it supports production and what it requires throughout operation.

 

Bring the Review into Your Production Specification

Before finalising the configuration, bring the operating cases, selected functions and site interfaces together. Record the purpose of the required routes and measurements, the expected automation behaviour and any questions still needing engineering review.

This gives the project team a common basis for discussing how the equipment will support the planned production process.

Peak Biotech’s column and chromatography system requirements checklists can help organise the available information. They cover operating conditions, equipment functions, materials, facility inputs and requested documentation or qualification support.

Use them to capture what is already defined and identify open points for the next technical discussion.

Download the column requirements checklist

Download the chromatography system requirements checklist

 

References

EU GMP Annex 15 Qualification and Validation. See the general principles and sections 3.2 and 3.3 on user requirements and design qualification. For active substance manufacture, Annex 15 may be used as supplementary optional guidance without introducing additional requirements to GMP Part II.